Next Week (11/19- 11/23):
- Plumbing, electrical, low voltage, water piping to be layed down.
- Masons to work on the foundation.
- Install the metal roof on the guest house/garage.
- Install the overhead door on the guest house/garage.
- Finish trimming out the windows in the guest house/garage.
Following week (11/26-11/30):
- Expects to backfill on either Tuesday or Wednesday
- Begin framing the new house by Wednesday, 11/28 - at this point the project is about 1 week ahead of schedule.
Pray for good weather in the upcoming weeks so they can get the house framed before winter really decides to come on.