Monday, October 1, 2007

Monday, October 1st - Barn Floor Poured

On Thursday, September 27th they poured the footings for the garage/guest house. See pictures below:





Today, they poured the floor. See pictures below:






Tomorrow, Tuesday, they plan to start working on the garage/guest house walls along with carpentry work in the barn.


Schedule calls for them to be backfilling the garage/guest house by week end and framing to start next Monday, October 8th. As you can see the roof trusses have already arrived.



Stay tuned as the week progresses.